| No | Title of Project | Location | Client | Consultants | Start Date | Finish Date | 
| 1 | 
 Water transmission line from "Bardsir" City to "Rafsanjan" City | Kerman | Kerman Water Authority | Halil Ab Consulting Engineers | 1990 | 1992 | 
| 2 | 
 Water transmission line from "Bukan" City to "Saghez" City | Kurdistan | West Water Authority | Ramab Consulting Engineers | 1991 | 1996 | 
| 3 | 
 Water transmission line from "Zarrineh Rud" Refinery to "Tabriz" City | West Azerbaijan | East Azerbaijan Water Authority | Mahab Ghods Consulting Engineers | 1992 | 1999 | 
| 4 | 
 Water transmission line from "Minab" City to "Bandar Abbas" City | Hormozgan | Hormozgan Water Authority | Mahab Ghods Consulting Engineers | 1994 | 1997 | 
| 5 | 
 High Pressure Water transmission line For "Meiduk Cooper Complex" | Kerman | National Iranian Copper Industry Company | Nipek Consultant Engineering | 2000 | 2002 | 
| 6 | 
 Water transmission line from "Bandar Abbas" City to "Qeshm" Island | Qeshm Island | Hormozgan Water Authority | Mahab Ghods Consulting Engineers | 2002 | 2006 | 
 
 















 No.64,Northen Sheikhbahaee Ave, Mollasadra       Ave. Tehran, Iran., P.O.Box :19936-74454
No.64,Northen Sheikhbahaee Ave, Mollasadra       Ave. Tehran, Iran., P.O.Box :19936-74454 Tel.: +(98 21) 88039009
Tel.: +(98 21) 88039009   
 